Labour productivity calculator: does the work match the attendance?

Twelve workers marked present, but the wall only grew by half a day's work. Enter today's attendance and quantity done to see output per man-day, labour cost per unit, and whether the gap is big enough to check before you pay wages.

✓ Free, no login✓ Works for any activity✓ Flags gaps over 20%

By the True Site Sync team · Last updated 28 October 2026

Labour productivity calculator

Example: 10 workers × 8 hours = 10 man-days. 120 m² of plaster ÷ 10 = 12 m² per man-day, against a plan of 15. Expected 150 m², done 120 m²: a 20% gap. Labour cost = ₹7,000 ÷ 120 = ₹58.33 per m².

The formulas

Man-days = workers × hours ÷ 8
Output per man-day = quantity done ÷ man-days
Labour cost per unit = (workers × daily wage × hours ÷ 8) ÷ quantity done
Expected quantity = planned output per man-day × man-days
Gap % = (quantity done − expected) ÷ expected × 100

What a big gap usually means

GapLikely reasonWhat to check
Within ±10%Normal day-to-day variationNothing
−10% to −20%Material waited for, a difficult area, reworkDelays in the DPR, the material GRN timing
Below −20%Inflated attendance, idle gang, or the plan was wrongHeadcount on site, photos, the thekedar's muster, before payroll
Above +20%Quantity over-recorded, or the planned rate was too lowMeasure again before billing

Where do planned output figures come from?

Your own past jobs are the best source: divide the quantity done by the man-days on two or three similar jobs. The Bureau of Indian Standards' IS 7272 gives reference labour output constants for building work, and many firms keep their own rate-analysis figures. Set one figure per activity and per gang, and review it monthly.

Check this every day, automatically

In True Site Sync, attendance (present, absent, half day, overtime) and daily progress quantities live in the same project. Activities carry a planned daily productivity, progress photos carry GPS location, and each worker's panel shows wages earned against payments. Muster-card PDFs show the total paid. You see the gap the same evening, not when the bill is due.

Frequently asked questions

How is labour productivity calculated in construction?

Divide the quantity of work done by the man-days used. Man-days = number of workers × hours worked ÷ 8. For example, 120 m² of plaster by 10 workers in 8 hours is 12 m² per man-day.

What is a man-day?

One worker working one standard 8-hour day. Two workers for 4 hours is also one man-day.

How do I calculate labour cost per unit?

Divide the day's labour cost by the quantity done. 10 workers at ₹700 = ₹7,000; ₹7,000 ÷ 120 m² = ₹58.33 per m².

How can I verify labour attendance before paying wages?

Compare the attendance with the work done that day. If output per man-day falls more than about 20% below your planned rate, check the headcount on site, the photos and the thekedar's muster before payroll.

Where can I find standard labour output figures?

Use your own past jobs first. IS 7272 from the Bureau of Indian Standards gives reference labour output constants for building work, and your rate analysis may have figures too.

Labour productivity kaise nikale?

Aaj ka kaam (quantity) ko man-days se bhaag dijiye. Man-days = mazdoor × ghante ÷ 8. Jaise 10 mazdoor, 8 ghante, 120 m² plaster = 12 m² prati man-day.

See the attendance-vs-work gap every evening

Attendance, daily quantities and wages in one app, so you check before you pay.

Start free 6-day trial

Or book a demo.