Construction schedule & Gantt chart: plan it in an afternoon

A useful site schedule isn't a 2,000-line file nobody opens. It's the right activity sequence per location, realistic durations, the links between tasks, and a 3-week look-ahead the site actually works to.

✓ Ready activity sequence✓ Look-ahead method✓ Gantt PDF export

By the True Site Sync team · Last updated 28 October 2026

In short. List locations (Block A, Basement, Tower 2). Give each one the standard activity sequence, set durations from your crew output, and link each task to the one it waits for. Draw it as a Gantt chart. Then run the site from a 3-week look-ahead and a daily labour plan.

Typical activity sequence for a building

#ActivityWaits for
1Site clearing and layout—
2Excavation1
3PCC2
4Footings (reinforcement, shuttering, concrete)3
5Columns up to plinth, plinth beam4
6Backfilling and plinth filling5
7Columns, then beams and slab, floor by floor6 / previous floor
8Brickwork / blockworkSlab above de-shuttered
9Electrical and plumbing conduits8
10Plaster9
11Flooring, doors and windows10
12Painting, fixtures, snagging, handover11

Adjust the sequence to your structure and specification. Waterproofing, MEP risers and external works run in parallel on most jobs.

Five steps to a schedule the site will follow

1. Break the job into locations

Plan by block, floor or zone, not just by activity.

2. Set durations from output

Duration = quantity ÷ (crew size × output per man-day). See the productivity calculator.

3. Link the tasks

Use finish-to-start links. The longest chain of linked tasks is your critical path.

4. Run a 3-week look-ahead

Every week, list the next three weeks' tasks and clear their constraints: drawings, material, labour, approvals.

5. Plan labour daily

Allocate gangs to tasks each day and compare with what got done.

Plan it in True Site Sync

The schedule builder is location-based. Create locations, drag standard construction tasks onto each timeline, and set duration, start and dependencies. Auto-Schedule fills in sequential dates, and you can duplicate a whole location for repeated floors and export a Gantt PDF. Planning tasks carry material requisitions and equipment, with checks for missing resources and clashes. Micro-planning allocates daily and weekly labour by trade and shows free labour for each day. Progress, delays and reasons flow into the DPR.

Frequently asked questions

How do I make a construction schedule?

Split the job into locations, list activities in their construction sequence, set each duration from quantity and crew output, link tasks to the ones they wait for, and draw it as a Gantt chart. Review it weekly with a 3-week look-ahead.

What is a Gantt chart in construction?

A bar chart with activities down the side and dates across the top. Each bar shows when a task starts and finishes, and links show which tasks wait for others.

What is the sequence of building construction?

Layout, excavation, PCC, footings, plinth, backfilling, then columns, beams and slabs floor by floor, followed by masonry, MEP conduits, plaster, flooring, doors and windows, painting and handover.

What is a look-ahead schedule?

A short-range plan, usually 3 weeks, taken from the master schedule. It lists the tasks coming up and the constraints to clear first: drawings, material, labour and approvals.

How do I calculate activity duration?

Duration in days = quantity ÷ (number of workers × output per man-day). For example, 600 m² of plaster ÷ (10 × 15) = 4 days.

Plan by location, export the Gantt

Drag tasks onto locations, auto-schedule, and track the plan against daily progress.