Typical activity sequence for a building
| # | Activity | Waits for |
|---|---|---|
| 1 | Site clearing and layout | — |
| 2 | Excavation | 1 |
| 3 | PCC | 2 |
| 4 | Footings (reinforcement, shuttering, concrete) | 3 |
| 5 | Columns up to plinth, plinth beam | 4 |
| 6 | Backfilling and plinth filling | 5 |
| 7 | Columns, then beams and slab, floor by floor | 6 / previous floor |
| 8 | Brickwork / blockwork | Slab above de-shuttered |
| 9 | Electrical and plumbing conduits | 8 |
| 10 | Plaster | 9 |
| 11 | Flooring, doors and windows | 10 |
| 12 | Painting, fixtures, snagging, handover | 11 |
Adjust the sequence to your structure and specification. Waterproofing, MEP risers and external works run in parallel on most jobs.
Five steps to a schedule the site will follow
1. Break the job into locations
Plan by block, floor or zone, not just by activity.
2. Set durations from output
Duration = quantity ÷ (crew size × output per man-day). See the productivity calculator.
3. Link the tasks
Use finish-to-start links. The longest chain of linked tasks is your critical path.
4. Run a 3-week look-ahead
Every week, list the next three weeks' tasks and clear their constraints: drawings, material, labour, approvals.
5. Plan labour daily
Allocate gangs to tasks each day and compare with what got done.
Plan it in True Site Sync
The schedule builder is location-based. Create locations, drag standard construction tasks onto each timeline, and set duration, start and dependencies. Auto-Schedule fills in sequential dates, and you can duplicate a whole location for repeated floors and export a Gantt PDF. Planning tasks carry material requisitions and equipment, with checks for missing resources and clashes. Micro-planning allocates daily and weekly labour by trade and shows free labour for each day. Progress, delays and reasons flow into the DPR.
Frequently asked questions
How do I make a construction schedule?
Split the job into locations, list activities in their construction sequence, set each duration from quantity and crew output, link tasks to the ones they wait for, and draw it as a Gantt chart. Review it weekly with a 3-week look-ahead.
What is a Gantt chart in construction?
A bar chart with activities down the side and dates across the top. Each bar shows when a task starts and finishes, and links show which tasks wait for others.
What is the sequence of building construction?
Layout, excavation, PCC, footings, plinth, backfilling, then columns, beams and slabs floor by floor, followed by masonry, MEP conduits, plaster, flooring, doors and windows, painting and handover.
What is a look-ahead schedule?
A short-range plan, usually 3 weeks, taken from the master schedule. It lists the tasks coming up and the constraints to clear first: drawings, material, labour and approvals.
How do I calculate activity duration?
Duration in days = quantity ÷ (number of workers × output per man-day). For example, 600 m² of plaster ÷ (10 × 15) = 4 days.
Plan by location, export the Gantt