RA Bill Format: running account bill format with a worked example

A clean running account (RA) bill format you can copy, the deductions in a sensible order, and a calculator that takes you from work done to net payable. For the step-by-step process, see our RA bill guide.

✓ Format to copy✓ Deductions in order✓ Based on CPWA Form 26

By the True Site Sync team · Last updated 13 October 2026

What is the format of an RA bill?

An RA (running account) bill lists each BOQ item with its unit, contract quantity, up-to-date measured quantity, quantity paid in previous bills and quantity in this bill, with rates and amounts. Below the items come GST and the deductions (retention, TDS, recoveries, penalties) to reach the net payable. In CPWD work, the running account bill is CPWA Form 26.

RA bill format: item table

SrItem no.DescriptionUnitBOQ qtyPrevious qtyThis bill qtyUp-to-date qtyRate (₹)Previous amountThis bill amountUp-to-date amount
12.1PCC 1:4:8m³220150341845,5008,25,0001,87,00010,12,000
25.1Plaster 12 mm CM 1:4m²4,0001,2008002,0003003,60,0002,40,0006,00,000

The logic is always the same: this bill = up-to-date − previous. Quantities come from the measurement book, and the up-to-date quantity of an item should never exceed what the BOQ and approved deviations allow.

CPWA Form 26: the three parts

PartWhat it contains
Part IAccount of work executed, abstracted from the measurement book (the item table above)
Part IISecured advances on materials brought to site (detailed in Form 26A)
Part IIIMemorandum of payments: totals, previous payments, deductions and the net amount

Related forms: Form 23 is the measurement book and Form 24 the first and final bill for one-time payments. On a running account, the final bill is also prepared on Form 26. Running payments are advances against the final bill. Under CPWD's conditions, RA bills can be held until the contractor's labour licence and EPFO, ESIC and BOCW registrations are in place (GCC copy). See contractor licence and registration.

RA bill calculator: from work done to net payable

Percentages apply to this bill's value excluding GST. Turn off anything your contract doesn't include (for example, GST TDS applies only to government bodies, and labour cess only where it's deducted from bills).

Worked example: deductions in order

LineWorkingAmount
Up-to-date value₹25,00,000
Less previous bills−₹15,00,000
This bill₹10,00,000
Add GST @ 18%+₹1,80,000
Gross₹11,80,000
Retention @ 5%on ₹10,00,000−₹50,000
Income-tax TDS @ 2%Section 393 (ex-194C)−₹20,000
GST TDS @ 2%CGST s.51, government work−₹20,000
Labour cess @ 1%where deducted−₹10,000
Mobilisation advance recovery−₹1,00,000
Net payable₹9,80,000

No official order of deductions is prescribed; this is a common convention. Your contract decides which deductions apply. Calculators for each: GST TDS, labour cess, liquidated damages.

Client bill vs subcontractor bill

The format is the same whether you're billing your client or certifying a subcontractor's bill; only the direction changes. For the subcontractor side, see subcontractor billing. For when payment falls due after you submit, see the RA bill payment timeline.

Make RA bills from measurements, not Excel

In True Site Sync, measurements become an abstract and an RA bill with exactly these columns: BOQ/PO quantity, previous quantity, this-bill quantity, total quantity, rates and amounts. GST, retention, TDS, advance recovery and LD apply automatically, and the bill exports as PDF or Excel. See RA bill software.

Frequently asked questions

What is the format of an RA bill?

A table of BOQ items with unit, BOQ quantity, previous quantity, this-bill quantity, up-to-date quantity, rate and amounts, followed by GST, deductions and the net payable.

Which CPWA form is used for a running account bill?

Form 26. Part I is the account of work done, Part II secured advances and Part III the memorandum of payments. The measurement book is Form 23.

How is the this-bill amount calculated?

Up-to-date value minus the value already paid in previous bills.

What deductions are made from an RA bill?

Commonly retention, income-tax TDS, GST TDS on government work, labour cess where applicable, advance recoveries, material recoveries and liquidated damages. Your contract decides which apply.

Is the final bill different from an RA bill?

On a running account contract, the final bill is also prepared on Form 26, with a certificate that it is in full and final settlement.

Can I make an RA bill in Excel?

Yes, using the columns above, but the previous-quantity carry-forward and deductions are where Excel errors creep in. Software that builds the bill from measurements avoids re-typing.

RA bill kaise banaye?

Har BOQ item ki naapi gayi up-to-date quantity se pichle bill ki quantity ghataiye, rate se guna kariye, GST jodiye aur retention, TDS, recovery jaise katauti ghatakar net payable nikaliye.

RA bills straight from your measurements

Measurements → abstract → RA bill, with previous quantities and deductions handled for you.