Why outdated drawings cause rework
Drawings arrive on WhatsApp
R2 sits three chats above R3. The foreman opens whichever one he finds first.
Old prints stay on site
Nobody collects the R1 print from the site office when R2 arrives.
No naming rule
"final_final_new.pdf" tells nobody which revision it is.
No record of who got what
When the wrong work is found, nobody can show which drawing was issued.
Drawing register format
A drawing register is the master list of every sheet on the project and its current revision. Keep one per project:
| Drawing no. | Title | Discipline | Rev | Rev date | Status | Issued to | Replaces |
|---|---|---|---|---|---|---|---|
| S-201 | Column layout, ground floor | Structure | R3 | 14-10-2026 | GFC | Site engineer, formwork subcontractor | S-201 R2 |
| A-104 | First floor plan | Architecture | R1 | 02-10-2026 | GFC | Site engineer, mason gang | A-104 R0 |
| P-301 | Plumbing riser diagram | MEP | R0 | 20-09-2026 | For approval | — | — |
Status values: Tender → For approval → GFC → Superseded → As-built. Only GFC sheets go to the site.
A revision naming rule that works on site
Example: S-201_R3_GFC_14-10-26.pdf
The revision number goes in the file name, not just the title block. A supervisor can then see it on a phone without zooming into the PDF.
Tender, GFC and as-built drawings: the difference
| Type | What it is | Build from it? |
|---|---|---|
| Tender drawing | Used for pricing the bid | No |
| For approval | Issued for client or consultant comments | No |
| GFC (Good for Construction) | Approved for execution | Yes |
| Superseded | Replaced by a newer revision | No. Keep it only as a record |
| As-built | What was actually built, after handover | Record only |
Six steps to keep every site on the latest drawing
1. One folder per project
Use subfolders for Architecture, Structure, MEP and Superseded. Never keep drawings in personal chats or email.
2. Log every sheet
Add it to the register before anyone gets a copy.
3. Supersede the same day
Move the old file to Superseded and collect the old print from site.
4. Tell the people who build it
Send a one-line note naming the sheet, the revision and what changed, to the engineer and the subcontractor.
5. Record the change against the work
When a revision changes work already done, log it as a change with its quantity impact. That's your claim for extra work.
6. Check weekly
Compare the register with the prints and files in use on site.
How True Site Sync helps
Each project has a Documents area with nested folders. Upload drawings, PDFs and photos and the whole team sees the same folder tree on every phone and computer. Files sit in private cloud storage, so a new revision uploaded at the office is there for the site engineer at once. The folder list syncs offline; opening a file needs a connection.
When a revision changes work on site, record it in progress tracking with "Drawing Revision" as the reason. Raise the extra items in the measurement book so they reach the RA bill.
Honest note: True Site Sync stores drawings in folders. It doesn't number revisions automatically or overlay two revisions. Use the naming rule and Superseded folder above.
Frequently asked questions
What is a drawing register in construction?
A master list of every drawing on a project with its number, title, discipline, current revision, revision date, status and who it was issued to. It is how you prove which drawing was current on any date.
What does GFC drawing mean?
GFC means Good for Construction: the drawing has been approved for execution. Tender drawings and drawings issued for approval should not be used to build.
How do you control drawing revisions on site?
Use one shared folder, a revision number in every file name, a drawing register, and a Superseded folder for replaced sheets. Collect old prints the day a new revision is issued.
What is a superseded drawing?
A drawing replaced by a newer revision. Keep it as a record, but nobody should build from it.
Can I manage construction drawings on a mobile app?
Yes. Keep drawings in a shared project folder that syncs to every phone, so site engineers always open the same latest set. True Site Sync has a project documents area for this.
Who pays for rework caused by a revised drawing?
If the client or designer revised a GFC drawing after the work was built, the rework is usually a variation. Record the revision date and the quantities affected so you can claim it under your contract.
One folder of drawings for every site
Upload once, and every engineer opens the same set on their phone.